Call nowWhatsAppEmail

Flat refurbishment Vienna every empty day costs rent.

Flat refurbishment Vienna: from the contractor who does the work — not from a broker.

Flat refurbishment Vienna: refurbishing a flat after a change of tenant costs €60 to €350 per square metre in Vienna. What matters is not the price per square metre but time: every month a 60 m² flat in Vienna stands empty costs around €900 to €1,300 in rent – usually more than the repainting.

Flat refurbishment means preparing a returned flat so that it can be re-let without compromise. This is not a construction project in the classic sense but a matter of sequencing. Technically, almost everything is routine – painting, floors, silicone, doors, electrics. The difficulty lies in lining up several trades one after another in a short time without waiting days, while documenting properly what was normal wear and tear and what was damage. Anyone who separates the two has solid grounds when dealing with the previous tenant. Anyone who does not loses the argument over the deposit – and the time along with it. If only individual jobs are needed rather than the whole flat, minor repairs are the right framework.
✓ Fixed price per flat✓ Photo documentation for the deposit✓ All trades in one go✓ Final clean included✓ Framework agreement for property managers

Why time costs more than materials

In a refurbishment, two blocks of cost are set against each other: the construction work and the lost rent. The second is regularly underestimated because it does not appear on any invoice.

Flat sizeTypical monthly rent, grossCost per week emptyConstruction work, Standard package
45 m² period building700–950 €approx. €175–2405.000–9.900 €
62 m² period building900–1.300 €approx. €225–3256.800–13.600 €
85 m² new build1.200–1.700 €approx. €300–4259.400–18.700 €
Flat refurbishment Vienna: costs 2026 – net price overview
Flat refurbishment Vienna: the prices from the table at a glance, as of 2026, net.

This gives a clear priority: a sequence that saves two weeks is worth around €500 for a 62 m² flat – and those two weeks almost always arise from waiting times between trades, not from the work itself. The painter waits for the floor layer, the floor layer for the electrician, the electrician for an appointment. That is why coordination is the real service.

The fastest sequence is not the one with the most people on site, but the one with the right order. Electrics and plumbing first, because they open up walls and floors. Then filling and painting, because no more dust may be created afterwards. Then floors, because they are the surface most likely to be damaged last. Finally silicone, fittings and the final clean. Reverse this order and you do the work twice.

If the flat is still full, the work begins with clearing it: house clearance Vienna – on request commissioned together with the refurbishment.

The three packages – and what sets them apart

To keep invoicing transparent for property managers, we work with three packages. They do not differ in quality, but in scope.

PackageScopeWhen it fitsPrice netDuration
RefreshRepainting, silicone joints, minor repairs, final cleanshort tenancy, flat returned well kept60–110 €/m²3–6 working days
Standardplus sanding or new floors, doors, fittings, socketstenancy of 5–15 years, normal wear and tear110–220 €/m²6–12 working days
Upgradeplus new bathroom or kitchen, electrics as per inspectionlong tenancy, fittings outdated220–350 €/m²10–20 working days
Category upgradeBathroom, heating, electrics for a higher fittings categorystrategic decision by the ownerafter site visit3–6 weeks

Why this tiering? Because the decision almost always comes down to the same point: is sanding enough or does the floor have to come out, and is the bathroom still lettable. Everything else is similar in every package. Anyone who already knows the flat before it is returned can make the decision at the handover itself – which saves further days.

Unit prices: what the items cost

ItemUnitPrice netWhat is included
Painting walls and ceilingm² wall area8–14 €Covering, filling small holes, two coats
Sealing nicotine or water stainsm²6–12 €Stain-blocking primer, otherwise the stain bleeds through
Repairing crackslinear m12–28 €opening, reinforcing, filling
Sanding and sealing parquetm²28–45 €three sanding passes, two coats of lacquer
Repairing parquetpc.35–90 €replacing individual strips
New vinyl or laminate floorm²45–80 €Material, laying, skirting boards
Renewing silicone jointslinear m8–15 €removing the old joint, cleaning, re-applying
Painting an interior doorpc.180–320 €sanding, priming, lacquering
Replacing an interior doorpc.420–650 €Door leaf, fittings, installation
Replacing switches and socketspc.25–45 €by a licensed electrical contractor
Electrical inspection reportlump sum250–550 €Inspection of the installation, report
Replacing the lock cylinderpc.90–220 €so that no old keys remain in circulation
Replacing a WC or washbasinpc.450–900 €Removal, installation, connection
Final cleanm²3–6 €Windows, bathroom, kitchen, floors, ready for viewings
Clearing items left behindlump sum250–1.500 €Removal, disposal with proof
Worked example 1 · 62 m² period flat, returned after 8 years, Standard package
Painting 190 m² of wall area, sealing stains€2,600
Sanding and sealing parquet, 48 m²€1,800
Doors, silicone, electrical inspection, minor repairs€1,450
Final clean, photo documentation€330

Total approx. €6,180 net, which is €100/m², completed in 8 working days. One additional month of vacancy would have cost more than €1,000 for this flat – more than the entire painting job.

Worked example 2 · 78 m², returned after 22 years, bathroom and floors renewed
Bathroom strip-out, disposal, preparation€3,400
New bathroom: tiles, plumbing via partner firm€11,800
New floors 62 m², doors, full repaint€9,900
Electrics as per inspection, final clean€2,600

Total approx. €27,700 net, which is €355/m², in 18 working days. After a 22-year tenancy this is no longer a refurbishment but an upgrade – and it determines the price bracket in which the flat can be offered again.

Normal wear and tear or damage: why the distinction matters

When a flat is returned, the same discussion arises time and again: what must the tenant pay, and what does the landlord bear? The legal assessment depends on the individual case and is a matter for a lawyer or the property manager – but the technical basis can be prepared properly. Three things are decisive: the documented condition, the length of the tenancy and whether the damage goes beyond what normal use produces.

Finding at handoverUsually classed asWhat the documentation must show
Yellowed walls after several yearsnormal wear and tearLength of tenancy, overall condition
Wall-plug holes to the usual extentnormal wear and tearNumber and distribution
Foot traffic marks on the parquetnormal wear and tearArea, depth of the marks
Deep scratches, burn marks on the flooroften excessive wearClose-up photo with scale, position in the room
Heavy nicotine discolourationdisputed, depending on the individual casePhotos, note on stain-blocking primer as extra work
Damaged tiles, sanitary fittingsoften excessive wearClose-up photo, replacement cost per item
MouldThe cause decides: building or useMoisture measurement, location, thermal bridge or ventilation
Missing fittings, alterationsCheck the obligation to reinstateComparison with the handover report
The evidence is created in the first hours after the handover – not at the end of the works. Once the walls are painted, it can no longer be proven what they looked like. That is why, before work begins, we photograph every defect with its position and a scale, and we structure the cost breakdown so that items for normal wear and tear and items for damage are shown separately. Whether anything is recharged, and how much, is decided by the property manager or the owner – we provide the basis.

Mould at handover: the most common point of dispute

No other finding leads to disputes as often. The reason: mould can have a structural cause or a cause related to use, and both look the same. From a construction point of view, however, it can be narrowed down.

SignsRather points toNext step
Mould in external corners, behind furniture on external wallsThermal bridge, structural causeMeasure surface temperature, mitigate the thermal bridge
Mould around window reveals after window replacementinsufficient air exchange after the renovationVentilation concept, rebate vents
Mould only in a bathroom without a windowUse and ventilationCheck the extractor, set the run-on time
Mould at the base of the wall with a salt linerising dampMoisture measurement, check damp-proofing
Mould after water damageLeakLocate the pipe, drying, then repair

If the infestation goes back to water damage, every refurbishment is preceded by building drying with a clearance measurement – only then is anything rebuilt.

What is wrong in every case: painting over it. A coat of paint over mould does not remove the infestation, it makes it invisible until the next heating season – and then the discussion is with the new tenant. The right way: clarify the cause, remove the affected material, treat the substrate, and only then seal it. Details on the mould remediation page.

The process, day by day

Using the Standard package as an example, 62 m², eight working days:

DayWhat happensWhy in this order
Day 0Site visit at handover, photos, measurementsSecure the evidence before anything is changed
Days 1–2Minor repairs, electrics, sanitary replacementanything that opens up a wall or floor comes first
Days 2–3Filling, cracks, stain-blocking primerthe substrate must be dry before painting
Days 3–5Painting walls and ceilingsno more dust may be created after this
Days 5–7Sanding and sealing floors or laying new onesthe floor is the most delicate surface, so it comes late
Day 7Silicone, fittings, lock cylinder, remaining workfinishing work after the floor
Day 8Final clean, after photos, handoverready for viewings, documented

The one point at which this sequence regularly tips over is sealing the parquet: it needs drying time, and during that time nobody may enter the flat. Anyone who schedules other trades in parallel loses exactly these days twice over. That is why the floor is either done at the very end or the flat is closed off for two days.

For property managers: the framework agreement

If you hand over flats regularly, you do not need individual quotes but fixed terms and predictable processes. What a framework agreement with us includes:

  • Fixed package prices per square metre for Refresh, Standard and Upgrade – calculable as soon as the tenancy is terminated.
  • Fixed response times: site visit within five working days, if needed on the day of handover, quote within two working days.
  • Consistent documentation: before and after photos, cost breakdown split between maintenance and damage, ready to transfer straight into your accounts.
  • One point of contact for all properties, even with several flats running in parallel.
  • Final clean included, carried out by our partner company, with no second contract needed.
  • Defect rectification window: if the new tenant raises an issue, it is dealt with in the same week.

In numbers, a framework agreement above all saves time: the coordination that would otherwise be repeated for every flat falls away. With fifteen flats a year, that means several weeks less vacancy – and that is the item that appears on no invoice and yet costs the most.

Category upgrade: when doing more pays off

With very old fittings, the same question arises at every handover: just refurbish or upgrade straight away? Technically the answer is simple – if the bathroom, electrics and heating are at the end of their service life anyway, the handover is the only time this can be done without a tenant in the flat. Under tenancy law the question is more complex, because the permissible rent can depend on the fittings category; this has to be checked in each individual case.

SituationRecommendationReasoning
Bathroom from the 1980s, functionalrefurbish, joints and tapsEffort out of proportion
Bathroom with leaking bath, old tilesrenewRisk of consequential damage, lettability
Electrics without an earth conductorrenewA safety issue, not a comfort issue
Gas boiler over 20 years oldCheck replacement, consider available subsidiesA breakdown in winter costs vacancy
Parquet sanded several times alreadylay newWear layer used up, sanding achieves nothing

Floors: what pays off when

In almost every refurbishment, the floor is the second-largest item after painting and the one where most wrong decisions are made. The reason: sanding is cheaper than relaying, but only works as long as there is wear layer left.

Floor typeHow often it can be sandedHow to recognise itRecommendation
Solid parquet, strip parquetseveral times, 8–12 mm wear layerindividual strips, often herringbonesand, as long as no gaps are opening up
Engineered parquetonce or twice, 2.5–4 mmClick joints, uniform appearancecheck the thickness before sanding
Laminatenot at allprinted surfacereplace
Vinyl or PVCnot at allsoft surface, welded seamsreplace, cheap and quick
Old floorboardsseveral timeswide boards, visible nailspreserve, repair, sand
Tiles––repair rather than replace, provided the design is acceptable

A common misconception concerns engineered parquet: it looks like solid parquet but has only a few millimetres of usable wood. If it is sanded for the second or third time, the backing board shows through and the floor is ruined. That is why the thickness is checked at a concealed spot before every sanding – a few minutes' effort that prevents thousands of euros of damage.

In economic terms: sanding and sealing costs €28 to €45/m², relaying with vinyl or laminate €45 to €80/m². So the difference is smaller than many people assume – and a new floor gives a uniform look that pays off immediately at viewings. With old floorboards and herringbone parquet, preserving them is almost always the better decision, because that very floor is the selling point of a period flat.

Painting: why the substrate determines the result

Painting is the item where most corners are cut and the one that costs money again the fastest. The reason almost never lies in the paint, but in the substrate.

SubstratePreparation requiredWhat happens if it is missing
Yellowed emulsion paintClean, one or two coatsCoverage insufficient, streaks remain
NicotineStain-blocking primer before paintingYellowing bleeds through after a few days
Water stainsCheck the cause, then sealStain comes back, often larger
Cracks in the wall or ceilingopening, reinforcing, fillingCrack shows through again after a few weeks
Old distemperremove completelynew paint peels off together with the old coat
Lime plaster in a period buildingchoose a breathable paintPlaster cannot breathe, damage at the base of the walls

This explains why a quote with the item “painting, lump sum” tells you little. Two quotes for the same flat can differ by a factor of two, and the difference lies in the preparation, which you can no longer see after completion – but certainly will four weeks later.

Bathroom and kitchen: refurbish or renew

At viewings, both rooms have a disproportionately strong influence on lettability, and both are the most expensive items. That is why a sober assessment is worthwhile, rather than renewing everything or leaving everything as it is across the board.

FindingsRefurbishing is enoughRenewal makes sense
Joints dark, silicone mouldyyes, renewing joints €8–15/lin. mno
Taps limescaled or drippingyes, replacement €180–450 eachno
Enamelled bath, dull or chippedto a limited extent, a coating only lasts so longyes, if the damage is deep
Tiling functional but datedyes, if the condition is flawlessif there are hollow spots or cracks
Waterproofing under the bath uncertainnoyes, consequential damage is likely
Kitchen units damaged, worktop swollenReplace partsrenew if there is water damage in the carcass

The most important point is in the second-to-last row: uncertain waterproofing is not a cosmetic issue but a risk for the flat below. Water damage from a leaking shower costs many times the renovation and also causes vacancy in two flats. So when in doubt, it is opened up and checked before new tiles go on. More on this on the bathroom renovation page.

The handover report: the basis for everything that follows

A good report saves more discussion later than any argument after the fact can win. These points belong in it, room by room:

  • Condition of every surface – wall, ceiling, floor, doors, windows, each with a short description rather than just “fine”.
  • Meter readings for electricity, gas and water, with date and photo.
  • Number of keys handed over, including cellar, bin room and letterbox.
  • Function check of boiler, drains, roller shutters and windows, with the date of the last service.
  • Defects with photos, each with a scale and its position in the room.
  • Alterations made by the tenant and whether reinstatement was agreed.

For the refurbishment, the last point is particularly relevant: fixtures the tenant leaves behind – lights, shelves, partition walls, a floor they laid themselves – must either be taken over or removed. Both cost money, and the decision belongs in the report, not in a later discussion.

What you can prepare yourself

If you want to keep the vacancy short, you can take care of a few things before the handover that would otherwise cost days:

PreparationWhenEffect
Fix the date for the site visit at handoveron terminationsaves 3–5 days
Decide on bathroom and floors in advancebefore the handover, after a viewingMaterials can already be ordered
Clarify access and key handoverbefore work beginsavoids idle time for the tradespeople
Inform the property manager about noisy working hoursbefore work beginsno complaints, no work stoppage
Prepare the listing, schedule photos after completionduring the worksLetting starts on the day of handover

The last point sounds trivial, but in practice it is the biggest lever: if the listing is only created after completion, another one to two weeks pass before the first viewing – the same time we painstakingly saved in the construction sequence beforehand.

How a flat ages – and what that means for planning

Every flat ages in stages, and anyone who knows the stages can anticipate the work needed at handover instead of discovering it. The following overview shows what typically appears after which length of tenancy.

Length of tenancyTypical conditionSuitable packageExpected cost per m²
up to 3 yearsWalls usable, floor intact, joints fineRefresh, often only partly40–80 €
3–8 yearsWalls yellowed, silicone worn out, floor with foot traffic marksRefresh to Standard60–150 €
8–15 yearsFloor needs sanding, doors worn, switches yellowedStandard110–220 €
15–25 yearsBathroom dated, electrics borderline, floor at the end of its lifeUpgrade220–350 €
over 25 yearsFittings completely outdatedCategory upgrade or renovationafter site visit

For property managers this produces a simple planning rule: for tenancies of more than 15 years, the handover budget should be set at upgrade level as soon as notice is given, not at repainting level. Anyone who calculates it the other way round ends up either over budget or with a flat let well below its potential.

Why one contractor for all trades is cheaper than three

On paper, awarding each trade separately is cheaper: each firm only prices its own work, and the sum of the individual prices is below the package price. In the final account this is regularly reversed, for four reasons.

  • Waiting days. In practice, every transition between two firms costs one to three days. With four trades that means up to two weeks of vacancy – around €450 to €650 for a 62 m² flat.
  • Interfaces. If the painter comes after the floor layer, he has to cover everything and works more slowly. If he comes before, the floor layer has to wait for it to dry. Both cost money, and neither is noticed by anyone because it does not appear as an item anywhere.
  • Responsibility. If there is a defect at the interface – paint on the new floor, scratches in the freshly painted wall – two firms point at each other. The client is left to sort it out.
  • Coordination effort. Four firms mean four appointments, four access arrangements, four invoices and four contacts. This time is not billed, but it is incurred – by the property manager.

That is why a comparison between separate contracts and a package is only fair once vacancy costs and internal effort are included. In our experience the threshold is three trades: below that, separate contracts pay off; above it, almost never.

What happens to the costs if something turns up during the works

Refurbishments are more predictable than full renovations, but not free of surprises. The three most common:

FindingsHow oftenApproachTypical additional costs
Damp behind furniture or built-in unitscommon after a long tenancyClarify the cause, then dry, then paint400–2.500 €
Damaged screed under the floor coveringoccasionallyrepair or level with filler15–40 €/m²
Electrics without an earth conductor in some areascommon in period buildingsInspection, decision on partial renewal800–4.500 €

We always handle this the same way: stop, take photos, submit a supplementary quote, wait for approval. Not because it sounds nicer, but because the alternative – carrying on and billing afterwards – regularly leads to disputes over items nobody approved.

What the landlord must maintain – and what not

From a construction point of view, the boundary can usually be clearly defined, even if the legal classification depends on the individual case. The landlord's maintenance obligation covers what keeps the flat usable: watertight windows and roof, working pipes, safe electrics, a usable bathroom, a working heat source. Anything beyond that which improves the fittings is a matter of choice, not obligation.

MeasureUsually maintenanceUsually improvement
Replacing a dripping tapyesno
Renewing a defective boileryesno
Replacing a 1985 bathroom with a modern oneno, as long as it worksyes
Repairing a leaking windowyesno
Replacing box windows with new windowsdepending on conditionoften yes
Renewing electrics without an earth conductoryes, a safety issueno
Relaying floors instead of sandingdepending on conditionfrequently yes

Why this matters in practice for the refurbishment: the breakdown we provide separates the items so that this allocation remains traceable. That makes accounting easier towards the owners, towards the reserve fund and – if necessary – towards the previous tenant. Which item is ultimately allocated to whom is decided by the property manager or the owner after legal review.

Materials: where quality matters and where it does not

A rented flat follows a different logic from an owner-occupied home. What matters is not the highest quality but the right balance between purchase price, service life and how easily it can be restored at the next handover.

Building elementRecommendationReasoning
Wall paintscrub-resistant qualitycopes better with the next change of tenant, costs hardly more
Floor covering in living areasrobust vinyl or laminate of a medium use classhard-wearing, replaceable in sections
Silicone jointswith fungicidal additivestays clean for longer, reduces complaints
Taps and fittingsStandard range from a well-known manufacturerspare parts available for years
Door fittingsmetal rather than plasticsurvives several tenancies
Tilesneutral formats and colourspartial repair possible, remains lettable

The last point is often underestimated: anyone who chooses an eye-catching format will no longer find a matching replacement tile after five years. A single damaged tile then leads to replacing the whole surface. In such cases, neutrally chosen standard products are the cheaper decision, even if they seem less interesting at the moment of choosing.

Handover to the new tenant

The final stage decides whether the refurbishment turns into a smooth re-letting. Three points have proven their worth:

  • Photo documentation after completion. It serves as proof of condition for the new handover – and saves discussion again at the next return.
  • Short defect period. Whatever the new tenant raises in the first few weeks is dealt with immediately. That is cheaper than a complaint that drags on for months.
  • Documents in one place. Electrical inspection report, boiler service, description of the floor build-up – collected at the property manager's, not scattered across several email inboxes.

This closes the circle: a documented refurbishment is not just a completed job, but the starting point for the change of tenant after next. Anyone who keeps this up has, after two cycles, a portfolio in which every handover can be planned – and that lowers costs more lastingly than any negotiated price per square metre.

Common mistakes in flat refurbishment

MistakeWhy it happensWhat it costs
Starting without photos before work beginsTime pressure at handoverno basis when dealing with the previous tenant
Commissioning trades separatelyeach individual price looks cheaperWaiting days, vacancy, coordination for the property manager
Painting over stains without stain-blocking primersaves one stepStain bleeds through, the room has to be repainted
Painting over moulda quick fix before the viewingReturns in the heating season, complaint from the new tenant
Sanding parquet although the wear layer is gonecheaper than relayingFloor ruined, relaying needed on top
Laying the floor before paintingthe floor layer had time earlierCovering work, damage, rework
Awarding the final clean separatelysupposedly cheaper with a cleaning firmadditional appointment, flat stays empty for longer
Electrical inspection only after lettingwanting to save costsWork in an occupied flat, more expensive and disruptive

What you get from us

  • Fixed price per flat after the site visit, broken down into items – not as a lump sum.
  • Before and after photo documentation, every defect with its position and a scale.
  • Separate cost breakdown for normal wear and tear and for damage.
  • One point of contact for all trades, even with several flats at the same time.
  • Final clean by our partner company, with no second contract needed.
  • Electrical inspection report on request, issued by a licensed electrical engineer.

When you do not need us

If only repainting is needed and the flat will be empty for several weeks anyway, a painting firm is sufficient – and in that case it is also the cheaper solution. We are worth it as soon as several trades come together, the re-letting needs to happen quickly or you, as a property manager, need a permanent partner for all flats in your portfolio.

Frequently asked questions about flat refurbishment in Vienna

How much does it cost to refurbish a flat after water damage?
That depends on whether only surfaces are affected or the build-up as well. Drying, removal of soaked materials and reconstruction usually range between €3,000 and €15,000 – the insurer requires damage documentation for this, which we provide as well.
Can the flat be viewed during the works?
Yes, from the point at which painting and floors are finished. Before that we advise against it: prospective tenants judge the condition they see, and a half-finished flat leaves a lasting impression, even if it is flawless afterwards.
What happens to fixtures installed by the previous tenant?
They are either taken over or removed – this is determined by the agreement in the lease and the handover report. Removal costs €250 to €2,500 depending on the scope, documented with photos before dismantling.
How is the price calculated for several flats at once?
Using fixed package prices per square metre from the framework agreement. For flats running in parallel in one building, there are additional savings from shared travel, materials and disposal, which we show in the quote.
Do you also carry out minor repairs during an ongoing tenancy?
Yes, for property managers with a framework agreement. The difference from a refurbishment: appointments are arranged with the tenant, work is done room by room and the effort is billed by the hour.
How long is your quote valid?
30 days from the date of issue. After that we recheck material and labour costs, because floor coverings and sanitary products in particular fluctuate in price at short intervals.
How much does refurbishing a flat after a tenant moves out cost?
€60 to €110/m² for a Refresh, €110 to €220/m² for Standard with floors and doors, €220 to €350/m² if the bathroom or kitchen is renewed. In our example, a 62 m² period flat on the Standard package comes to around €6,180 net.
How quickly can the flat be let again?
With a Refresh in 3 to 6 working days, with the Standard package in 6 to 12 working days, with an Upgrade including the bathroom in 10 to 20 working days. What matters is that the trades follow one another without waiting days.
Why is vacancy more expensive than painting?
Because the costs keep running while no rent comes in. For a 62 m² flat that is around €225 to €325 per week. Two weeks saved therefore roughly equal the cost of completely repainting one room.
In what order is the work carried out?
First everything that opens up a wall or floor: electrics and plumbing. Then filling and painting. Then floors. Finally silicone, fittings and the final clean. Anyone who does the floor first has to cover it afterwards and damages it anyway.
Can I recharge the costs to the previous tenant?
Only for damage that goes beyond normal wear and tear, and that is a legal question for the individual case. We provide the basis: photos of every defect before work begins and a breakdown that shows both categories separately.
What counts as normal wear and tear?
Everything that inevitably arises from use in line with the lease – walls yellowed after years, wall-plug holes to the usual extent, foot traffic marks on the floor. Deep scratches, burn marks or damaged sanitary fittings are generally not included.
When should the photos be taken?
At the handover, before any work. Once the walls are painted, the previous condition can no longer be proven. Ideally together with the handover, so that both parties see the same thing.
What happens if there is mould in the flat?
First the cause is narrowed down: thermal bridge, ventilation, rising damp or a leak. Only then is it remediated. Painting over it is no solution – the infestation returns in the next heating season.
Do you work with property managers?
Yes, with a framework agreement: fixed package prices, fixed response times, consistent documentation and one point of contact for all properties. Above all, this saves the coordination that would otherwise start afresh with every flat.
What is included in the final clean?
Windows including frames, bathroom and WC, kitchen, floors and surfaces – ready for viewings. It is done by our partner company directly after the works, without you having to organise a second appointment.
Do I need an electrical inspection report when re-letting?
An up-to-date report documents the condition of the installation and protects the landlord. We arrange it through a licensed electrical engineer, €250 to €550. It makes sense before letting, because work is easier in an empty flat.
Is a category upgrade worthwhile?
If the bathroom, heating and electrics are at the end of their service life anyway, the vacancy period is the only cost-effective moment. Whether this affects the permissible rent has to be checked under tenancy law – we provide the structural basis and the fixed price.
What happens to furniture left behind?
We clear it and dispose of it with proof, €250 to €1,500 depending on the volume. We document valuable items beforehand so that there is no discussion later.
Do you also change the locks?
Yes, on request we replace the cylinder of the flat's front door, €90 to €220. This makes old keys worthless – recommended at every change of tenant.
Can parquet always be sanded?
No. Solid parquet can take several sandings, engineered parquet often only one, depending on the wear layer. Once the wear layer is used up, sanding no longer helps – then a new floor is laid.
How long does sealing the floor take?
Depending on the system, one to two days until it can be walked on. Nobody should enter the flat during this time, which is why the floor is done at the end and not in parallel with other trades.
Do you also carry out partial refurbishments?
Yes, for example only the bathroom or only the floors. The “Refresh” package covers the most common work after a short tenancy; everything else is priced individually.
Can several flats be done at the same time?
Yes. For property managers with several properties, we schedule the trades so that they rotate between the flats – which results in fewer waiting times than working through them one by one.
How much does it cost to repaint a flat?
€8 to €14 per square metre of wall area; for a 62 m² flat that is around 190 m² of wall area and therefore €1,500 to €2,700. If stains have to be sealed, add €6 to €12/m².
Who is liable if the new tenant notices something?
Our work is covered by the statutory warranty. If something attributable to our work is raised within this period, we put it right – under framework agreements in the same week.
How do I get the fixed price?
Within two working days of the site visit, as a package price with individual items. Supplements only after written approval – and only if something becomes visible on opening up that could not be seen beforehand.
Why do you not give a price over the phone?
Because it would be wrong. The effort depends on the condition, and that can only be seen in the flat. A price over the phone is either too high or it does not hold – neither helps anyone.
Can you come on the day the flat is handed back?
Yes for property managers with a framework agreement, otherwise within five working days. The earlier the site visit, the sooner the flat is back on the market.
When does it stop being a refurbishment?
As soon as installations are replaced, floor plans are changed or the bathroom and kitchen are renewed. Then we speak of apartment renovation – a different scope, a different duration, a different calculation.
Do you also take on flats outside Vienna?
In Klosterneuburg and the area surrounding Vienna, yes. Further afield, a travel surcharge is added, which is shown in the quotation.

Related services

◆ Partner company · Bling Premium Reinigung

Flat refurbished? The final clean is already scheduled.

After every refurbishment, our partner company Bling Premium Reinigung takes care of the final clean – windows, bathroom, kitchen, floors, ready for viewings for the re-letting. More at bling-bling.at.

Send enquiry

Enquire directly here — fixed-price quotation free of charge. Skyline Bau replies within 2 working days.

Enquiry about: flat refurbishment Vienna
Construction emergency? Water damage, mould, acute damage — please contact us directly via WhatsApp 24/7 — we will come promptly.

You and Skyline Bau will each receive a confirmation by email.

Ready for your flat refurbishment in Vienna?

Write to us directly on WhatsApp — send photos. Reply within 2 working days.

Bling Bling GmbH · Skyline Bau brand · Company details in the legal notice

Note: Skyline Bau is the brand name of the construction and renovation division of Bling Bling GmbH and not a separate legal entity. The sole contractual partner is Bling Bling GmbH. Bling Bling GmbH is a restricted building trade business under § 99 GewO (Austrian Trade Regulation Act) and not a licensed master builder (konzessionierter Baumeister). Under § 99 (5) GewO, the title „Baumeister“ (master builder) is reserved for businesses licensed under § 94 no. 5 GewO. Regulated trades — master builder services, structural engineering, gas and plumbing, electrical engineering — are carried out exclusively by authorised, licensed partner firms.